For partners that build or integrate commercially available applications and service solutions with the Oracle Cloud Platform
For partners that provide implementation or managed services around Oracle Cloud Applications
A client is implementing Self Service procurement and Purchasing without inventory.
All the items are expense items with majority of the purchases are category based. Few capex purchases.
The accruals are setup for period end.
Thanks.
There is change order(XX)exist against PO (***) and which are having status either Incomplete/Pending Approvals or Approved.
Requirement : If new line are been added in to change order(XX) then it should always follow the newly added lines (cost center) approval hiearachy.
Rules are written on amount changed at header level including the cost center numbers with respect cost center manger approvals and which is working fine.
User needs that,if there is additonal line added in the change order then it should only follow the added lines cost center manager approvals not the exisiting lines cost center approvers.
Is there any attributes where We can compare the cost center with existing lines cost center and build approval hieararchy around it.
Can any one help on the same.
Hi All,
I really need some feedback on this topic. Below is the scenario I am working on:
1. I am creating an Expense Requisition Manually.
2. I have Buyer Assignment Rule for this Category.
3. When I approve the requisition, I can see buyer is also getting assigned in the requisition based upon Buyer assignment rule.
4. But I am not able to see requisition on Process Requisition page.
5. If I run Generate Orders Program, then I can see requisition on Process Requisition Page.
I have done multiple Cloud Procurement Implementations and have never used Generate Orders program for requisitions to appear on Process Requisition page.
In my current Project also, we never used Generate Orders process for Manual Requisitions to appear on Process Requisition page earlier.
But after recent upgrade to 19B, we have to run Generate Orders program for manual requisitions to appear on Process Requisition page.
Oracle Support engineer says this was always supposed to be working like this, which I don't agree with.
I have a requirement to define a value set in PO Distribution level and such value always the same as the PO charge account segment3.
SELECT cc.segment3 DEPT,
FROM po_distributions_all po_dis,
gl_code_combinations cc
WHERE po_dis.CODE_COMBINATION_ID = cc.CODE_COMBINATION_ID
and po_dis.po_distribution_id = ?????? (screen UI)
We have an existing Purchase Order Distributions DFF that was configured with a Display Property of List of Values with a Validation Value Set. Due to a change in business process, the business owners would like to change this DFF to be a Text Box without a List of Values associated with it. Is it possible to modify the DFF Segment Value Set and Display Properties to be a Text Box?
Current Configuration screen shots are included for reference.
Hi Experts,
This questions is precisely from Procurement and Finance FBDI and ADDFi prospective.
Is there a predefined limit for number of records (data) that we can use in FBDI and ADFDi while we upload the data using spreadsheet? If yes, do we have any standard oracle document around this indicates this information?
Also, is there a setup hosted by Oracle that we can increase or decrease this limit ?
Appreciate your help !!!
Regards,
Ujas
Hi,
We are trying to uncheck the Automatically generate orders option by default in BPA.
Currently its checked for all BPA's as shown in attached screen. We want it to be unchecked by default.
Any suggestions on this?
Thanks,
Nishanth
Is there a way to change the supplier after the PO is fully approved and in Open status.
Business requirement:
We have 2 suppliers with almost same name with minor difference in their names, so buyer selected the wrong Supplier and created a PO and now it has been fully approved. Now, we found that the PO should have been created with the other supplier. So, is there a way or custom role that allows buyer to change supplier during change order process.
We have a requirement from a supplier to create a 3 year purchase order. Since the balance is to be paid over a 3 year period, we do not want the entire balance encumbered immediately when it is created as that would mis-represent our actual current year encumbrance/obligations. Any thoughts on how to accomplish this?
Hello,
Although the PO status gets updated automatically to CLOSE once full PO is received and invoiced however our requirement is the the PO should be automatically changed to final close status either immediately along with the close status or lets say after certain duration which we should define.
Is it possible? is there any work around?