    Process to cancel or nullify pre-commitments on Requisitions...45.0
    Topic posted August 10, 2018 by AshokBlack Diamond: 60,000+ Points, tagged Budget/Encumbrance, FAQ, Requisition Processing, Tip in Procurement > Self Service Procurement public
    Title:
    Process to cancel or nullify pre-commitments on Requisitions at year end
    Summary:
    At year end close, process to cancel or nullify pre-commitments on Requisitions
    Content:

    Question:

    During year end close, how can we cancel or nullify pre-committed funds on requisitions to make those funds available later?

    Recommendation:

    The Cancel Requisition Lines in Spreadsheet downloads approved requisitions not yet liquidated in an ADFdi spreadsheet; Using the spreadsheet, users can mass cancel these lines to free up reserved funds.

  • Ashok
    How does partial processing to an Order work on a Budget...35.0
    Topic last edited July 28, 2018 by AshokBlack Diamond: 60,000+ Points, tagged Budget/Encumbrance, FAQ, Requisition Processing, Tip in Procurement > Self Service Procurement public
    Title:
    How does partial processing to an Order work on a Budget Controlled Requisition
    Summary:
    Impact of partially processing a budget controlled Purchase Requisition into a Purchase Order
    Content:

    I wanted to share some insight into how a budgetary controlled purchase requisition works for order processing. This was a recent customer question (and I have seen similar ones before) and thought it might be good to remind customers of behavior. 

    Specific Scenario:

    The purchase requisition contains a line for quantity 50 Units

    This requisition is processed into a purchase order

    The order is processed only for quantity 30 Units

    Question:

    What happens to the remaining quantity 20 Units on the purchase requisition

    Expected Behavior:

    When a purchase order is created from a requisition line, in the above scenario, two things happen:

    a) The entire Quantity 50 Units will be liquidated on the requisition line

    b) The purchase order will reserve the Quantity of 30 Units

    You cannot split that requisition that is budgetary controlled further.

    Also, current behavior does not support one requisition line to process into multiple purchase orders.

    =========================================================================================================

    As always please share feedback and ratings to help us evaluate the usefulness of these articles.