    modify the field content of an activity that is already started?
    Summary:
    modify the field content of an activity that is already started?
    Content:

    HI

     I have a query, is it possible to modify the field content of an activity that is already started?

    That is to say if the order was initiated, and through an API (for example) I can update the notes of the order (which is initiated)

    Thank you.

    Best Comment

    Zsolt Tolgyesi

    Hi Erlin,

    IMO yes it's possible without any issue. Only "completed" status is deny the activity update.
    https://docs.oracle.com/en/cloud/saas/field-service/19b/cxfsc/op-rest-ofsccore-v1-activities-activityid-patch.html
    Some properties cannot be updated include date, status, resourceId, activityId, positionInRoute, and custom file properties.

    Regards,
    Zsolt