    Action List is incomplete
    Content:

    Hello,

    The Supplier Change Request Approval Task Actions does not list all the actions enabled under this task in BPM.

    Example: In BPM, Delegate option is marked to assignees who have access to this notification. But the worklist for the assignee does not list Delegate as an option for this task.

    Comment

     

    • Alan Ng

      We will review and update this post.

    • Piyush Singh

      Hi Arun,

      Do you see Reassign action? If you do, try to reassign and see if you get option to chose between reassign and delegate.

      Thanks,

      Piyush

    • Arun

      Hello Piyush,

      First Level approver does not see the Reassign option. If First Level Approver escalates, then the Manager will be able to reassign.

      Delegate is not an option in either case.

      Thanks,

      Arun