    Topic posted May 15, 2017 by William KnowlesSilver Medal: 2,000+ Points, tagged Project Management 
    56 Views, 1 Comment
    Title:
    Asset Assignment at Middle-Level Task
    Summary:
    Unable to assign assets to a middle-level task in PPM
    Content:

    We have a use case where we would like to create/assign assets at a middle-level task in our work breakdown structure.  It appears that currently (Fusion R11) you must assign the asset either to a top or lowest-level task.  Do other customers have a similar use case?  Is there an enhancement request or plan for this functionality in the Fusion PPM road-map?

    Image:

    Comment

     

    • Dustin Grabowski

      Bill,  we have not heard of other use cases for the ability to assign assets at a middle-level task.  The ability to do so is not currently on our roadmap.  Please feel free to log an enhancement request that documents the requirements and use cases in detail.