    Hello - does anyone happen to have a days on hold formula for OBI in the legacy recruiting environment? 

    Comment

     

    • Kiran Shenvi

      Hi,

      If you are looking for Req. Total Days on Hold then in OBI Recruiting its as below :

      EVALUATE('RL_REQTIMEBETWEEN_FNC(%1,LOCALTIMESTAMP,%2,0,0,0,NULL)' AS DOUBLE,"Requisition Dates"."Req. Creation Date","Requisition Identification"."Req. Identifier")-EVALUATE('RL_REQTIMEBETWEEN_FNC(%1,LOCALTIMESTAMP,%2,1,0,0,NULL)' AS DOUBLE,"Requisition Dates"."Req. Creation Date","Requisition Identification"."Req. Identifier")

      Regards,