    Topic posted December 13, 2018 by PravinKumar MunnaluriRed Ribbon: 250+ Points, tagged Approvals 
    102 Views, 2 Comments
    Title:
    How to setup PO approval rules based on Project task
    Summary:
    How to setup PO approval rules based on Project task
    Content:

    Hi All,

    Currently we have configured PO approval rules based on Project level starting with Project manager as approver.

     However as per my business requirement we are having managers for each task with in the project.  Is there any way we can assign task managers at project task configuration and can we use those values in Po approval rules?

    Regards

    Pravin  

    Version:
    18B

    Comment

     

    • Ivan Pena

      Hi PraviKumar,

      Support for requisition & purchase order approval routing based on Project Task Manager is planned for a future release.

      Ivan

      • Mohammad Arif Zaffar

        Hello, 

        Is the below feature the solution for above question in 19D?

        If yes, appreciate if you share a white paper, demo/video or training material about how to use this feature. in the readiness, information is very limited.

         

          ROUTE PURCHASE ORDERS FOR APPROVAL TO PROJECT TASK MANAGERS