If i create a requisition with check funds(warning mode) and i have an agreement PO is generated automatically.
The problem is when PO is generated automatically funds check do not happens again.
If i do the same without an agreement when i go to Purchase Order and submit funds check are performed normally.
Does any one know if that is a BUG ?
Comment
Ivan, funds check is performed implicitly or explicitly on the requisition to reserve the funds, and gets liquidated when the PO is correspondingly created. Is your requisition not showing liquidation when you are generating the PO against it when an agreement is referred?
Can you please elaborate your situation a bit further?
Average Rating:



1 rating
|
Sign in to rate this
See the scenario below.
1. A Purchase Agreement is created and approved.
2. A Purchase Requisition is created for the item contained in the Agreement. When checking funds, the system returns the warning message. Insufficient funds. When submitting the Requisition for approval the system generates a commitment in Budget Control.
3. The Purchase Order is automatically generated linked to the Requisition and Purchase Agreement. When you click verify funds, the system returns the message Funds Approved.
That's the scenairo.
If value in Purchase Order is bigger that requisition funds check starts again
If value is the same or smaller funds check in PO does not happens again and document goes approved and not warning.
Why PO do not check funds again? They need to at least show message for buyer showing funds still warning.
Be the first to rate this
|
Sign in to rate this
See the scenario below.
1. A Purchase Agreement is created and approved.
2. A Purchase Requisition is created for the item contained in the Agreement. When checking funds, the system returns the warning message. Insufficient funds. When submitting the Requisition for approval the system generates a commitment in Budget Control.
3. The Purchase Order is automatically generated linked to the Requisition and Purchase Agreement. When you click verify funds, the system returns the message Funds Approved.
Be the first to rate this
|
Sign in to rate this
See the scenario below.
1. A Purchase Agreement is created and approved.
2. A Purchase Requisition is created for the item contained in the Agreement. When checking funds, the system returns the warning message. Insufficient funds. When submitting the Requisition for approval the system generates a commitment in Budget Control.
3. The Purchase Order is automatically generated linked to the Requisition and Purchase Agreement. When you click verify funds, the system returns the message Funds Approved.
That's the scenairo.
If value in Purchase Order is bigger that requisition funds check starts again
If value is the same or smaller funds check in PO does not happens again and document goes approved and not warning.
Why PO do not check funds again? They need to at least show message for buyer showing funds still warning.