    Raul Islas
    Budgetary control at Top resource
    Topic posted October 11, 2019 by Raul Islas, tagged Project Costing, Project Planning, Budgeting, & Forecasting 
    31 Views, 1 Comment
    Title:
    Budgetary control at Top resource
    Summary:
    I want to have budgetary control at top resource level
    Content:

    Hi,

    Im implementing PFM and i want to have budgetary control at resource level.

    I´ve created Financial Plan Type with Budgetary control enabled (Project=Absolute, Top Resource= Absolute)

    But when im creating a requisition, the validation funds is being done at project level.

    Do you know if some configuration is missing?, im attaching a word with the screens of my configurations and one sample of my budget structure of one of my projects.

    Regards.

     

    Version:
    19c
    Image:
    Document:

    Comment

     

    • Daniela Crisan

      Have you tried to Create the requisition at the lowest level task in order to see the project task in the Requisition ?