Field Service

Get Involved. Join the Conversation.

Topic

    Dilip Jayachandra
    sequential activities
    Topic posted August 9, 2018 by Dilip JayachandraBronze Medal: 1,250+ Points 
    24 Views, 2 Comments
    Title:
    sequential activities
    Content:

    Hi Gurus,

    How will we do sequential activities, where one activity is completed by a team automatically assign to another team.

    Thanks,

    Dilip

    Comment

     

    • Hardik Gupta

      Hi Dilip,

       

      There is an option to Link Activities.

      You need to create the activity link: Second activity starts after the first one is finished

      Activity 1 ---> Activity 2

      Assign "activity 1" to Person A and assign "activity 2" to Person B.

      Person B will not be able to start the activity until Activity 1 is completed.

      Refer Link Templates : Configurations-->Link Templates

       

      Regards,

      Hardik

    • Dilip Jayachandra

      Hi Hardik,

      I have tried the same in link activity, but there is no restriction as to only when the person A completes the activity Person B has to start.

      Thanks,

      Dilip