    Can't rebaseline
    Topic posted April 3, 2019 by Kim PulsSilver Medal: 2,000+ Points, tagged Grants Management, Project Contracts, Project Costing, Project Management 
    65 Views, 1 Comment
    Title:
    Can't rebaseline
    Content:

    I have a project that I need to rebaseline but it won't. Version 1 has a status of Original Baseline, then versions 2-4 are all Baseline. I'm not sure what the end-user was doing but none of them are Current Working and that is what I need the most recent version to be so we can get the budget dates in sync.

    Comment

     

    • Heather Hicks

      Hi Kim, 

      From the 'Manage Project Budget' page you should be able to highlight the current baseline and click on the duplicate icon. That will copy your current baseline and make a 'current working'. Make the changes there and if you save and close it will show "Current Working" or baseline directly from where you were editing it. Just a quick tip too: double check your version name because our's defaults to "Version 1" but you can change it from that edit screen. I hope that helps! 

      Thanks, Heather