    Sam Napoli
    What are Simultaneous Resources?Answered
    Topic posted December 6, 2018 by Sam NapoliRed Ribbon: 250+ Points, tagged Manufacturing MDM 
    280 Views, 4 Comments
    Title:
    What are Simultaneous Resources?
    Summary:
    What are Simultaneous Resources?
    Content:

    When assigning Resources to a Standard Operation, there is a Principal checkbox. The Using Manufacturing guide says" The indicator that a resource is the principal resource within a group of simultaneous resources. The simultaneous resources must have only one resource designated as principal resource." What are simultaneous resources, how do I set them up and how do they work? I can't find anything about that.

    Version:
    18b

    Best Comment

    Alexander Vaidhyan

    Simultaneous resources are a group of resources which share the same sequence number within a work order operation. All scheduled resources which share the same sequence number are scheduled in parallel together. All scheduled resources which share different sequence numbers are scheduled in series in the ascending order of the sequence number.

    For Example consider the following resources associated to Operation Sequence #10 of WO #1

    1. Res Sequence: 10

        Resource Name: Technician

        Usage: 1 hour

        Activity: Setup

    2. Res Sequence: 20

        Resource Name: Lathe

        Usage: 2 hours

    3. Res Sequence: 20

        Resource Name: Operator

        Usage: 2.5 hours

    In the above example, Work order scheduling will first schedule Technician Resource for 1 hour. This would be followed by scheduling both the lathe resource and operator resource in parallel for 2 hours and 2.5 hours respectively. So overall scheduled duration of Operation # 10 = 1 hour + Max of (2, 2.5)  hours = 1 + 2.5 = 3.5 hours.

     

    Hope this clarifies. There is a worked example for Scheduling in the user guide and a brief explanation of simultaneous resource. Please refer attached screenshot for simultaneous resource.

    Thanks and Regards

    Alex

     

     

     

    Comment

     

    • Alexander Vaidhyan

      Simultaneous resources are a group of resources which share the same sequence number within a work order operation. All scheduled resources which share the same sequence number are scheduled in parallel together. All scheduled resources which share different sequence numbers are scheduled in series in the ascending order of the sequence number.

      For Example consider the following resources associated to Operation Sequence #10 of WO #1

      1. Res Sequence: 10

          Resource Name: Technician

          Usage: 1 hour

          Activity: Setup

      2. Res Sequence: 20

          Resource Name: Lathe

          Usage: 2 hours

      3. Res Sequence: 20

          Resource Name: Operator

          Usage: 2.5 hours

      In the above example, Work order scheduling will first schedule Technician Resource for 1 hour. This would be followed by scheduling both the lathe resource and operator resource in parallel for 2 hours and 2.5 hours respectively. So overall scheduled duration of Operation # 10 = 1 hour + Max of (2, 2.5)  hours = 1 + 2.5 = 3.5 hours.

       

      Hope this clarifies. There is a worked example for Scheduling in the user guide and a brief explanation of simultaneous resource. Please refer attached screenshot for simultaneous resource.

      Thanks and Regards

      Alex

       

       

       

    • Sam Napoli

      Thanks Alex. That's extremely helpful. And how does he Principal checkbox affect the system? Taking the example above, what happens if you make the Lathe the Principal resource? 

    • Alexander Vaidhyan

      This flag identifies one of the resources in the simultaneous pool as principal. Functionally this flag does not influence the current behavior of the application, although it is used in the background to build the relationship between the prior resource and the simultaneous resource pool while scheduling.

    • Sam Napoli

      Thanks Alex