Order Management

Get Involved. Join the Conversation.

Topic

    Rommel Ben Vasquez
    The request date passed to order promising is outside the...
    Topic posted September 9, 2019 by Rommel Ben VasquezBronze Medal: 1,250+ Points, tagged Global Order Promising, Order Management 
    36 Views, 1 Comment
    Title:
    The request date passed to order promising is outside the range of the planning horizon. (DOO-2685269)
    Content:

    We have an order with requested (ship) date set in the future. The same order was submitted and the line got into scheduling error with the message. "The request date passed to order promising is outside the range of the planning horizon. (DOO-2685269)" 

    Where can we check to determine the "range of the planning horizon? What drives this which lead to the scheduling failing on order line with a request date in the future. The item has available on hand.

    Comment