    Project budget versionAnswered
    Topic posted November 7, 2018 by Xianyang XiaRed Ribbon: 250+ Points 
    97 Views, 2 Comments
    Title:
    Project budget version
    Summary:
    As a project budget version ,what's the "Current Working Version"?
    Content:

    There are several version of project budget.Working,current working , current baseline.What are the versions' meaning , and what's the difference between then?

    Best Comment

    John May
    A working version of any financial plan is essentially in 'draft' mode.  You can have many working versions; therefore
    
      *   If there is only one working version it will always be the 'current'.
      *   To edit specific version, you designate one working version as current.
         *   Only one version can be designated as 'current' (just like baselined budgets and published forecasts)
         *   As the current version, the user is allowed to edit
         *   Furthermore, there are certain reports that specifically identify the current working version.
    

    Comments Are Closed

     

    • Maureen Bradley

      I think you will find the clarifications and flow you are looking for here:

      https://docs.oracle.com/en/cloud/saas/project-portfolio-management/18c/oapfm/project-control-configuration-overview.html#OAPFM87297

       

    • John May
      A working version of any financial plan is essentially in 'draft' mode.  You can have many working versions; therefore
      
        *   If there is only one working version it will always be the 'current'.
        *   To edit specific version, you designate one working version as current.
           *   Only one version can be designated as 'current' (just like baselined budgets and published forecasts)
           *   As the current version, the user is allowed to edit
           *   Furthermore, there are certain reports that specifically identify the current working version.