    Kim Puls
    HCM feeds/areas into PPM
    Topic posted December 19, 2018 by Kim PulsSilver Medal: 2,000+ Points, tagged Capital Projects, Grants Management, Project Management, Project Performance Reporting, Project Resource Management 
    82 Views, 1 Comment
    Title:
    HCM feeds/areas into PPM
    Content:

    We are looking at the following areas that says they will flow into PPM:

    Jobs/positions, hierarchies, locations & competancies

    As I know PPM (Awards/Contracts/Projects) now, I can't figure out how this information would be used in PPM and then know how to test it.

    If we don't need theses areas, can they be turned off. We did experience (for p-cards only) that if an assignment change occurred for an individual...any p-card charges prior to the change were not longer recognized as valid even though that person didn't have a break in service...just an assignment change. UW is not using resource management for personnel.

    Kim

    University of Wyoming

    Comment

     

    • Alexandru Eremia - Oracle

      Hi Kim,

      The areas that you are looking for: Jobs/positions, hierarchies, locations & competencies

      may be useful in Oracle Fusion Project Resource Management when getting the resources evaluated by the staffing owner for a new project assignment.

      Please see:

      http://docs.oracle.com/cloud/latest/projectcs_gs/OAPEM/OAPEM1122104.htm#OAPEM1122104

      Resource Qualifications

      One measure of a resource's suitability for a project assignment is whether the resource has the qualifications and proficiency levels that are specified on a project resource request. Administrators set up qualifications and proficiency levels when they set up the workforce in Oracle Fusion HCM.

      Regards,
      Alex-Oracle