Hi Folks,
How to send PO to Supplier once it approved?
How to enter CC email id.
Any setup document would be appreciated
Comment
Hi Piyush,
Have a read of: Most Common Questions For View PDF/Communicate Purchase Order/Agreement to Supplier (Doc ID 1392241.1)
Regards,
Andrei
Average Rating:



1 rating
|
Sign in to rate this
Hi Andrei,
i have gone through but i am in initial phase. i did setup email id at supplier site as well as PO Header level, but still i am not getting emails.
Average Rating:



1 rating
|
Sign in to rate this
-What communication method do you have set for supplier site?
-for Worklist - Notification Mode- do you have ALL or EMAIL?
-Please also check profiles mentioned on Purchase Order Communication: How to To Enable/Disable Purchase Order Communication With The Supplier And/Or Override The Default Supplier E-mail? (Doc ID 2237654.1)
-If you open the PO from UI and you try via: Actions - Communicate, is this sent?
Regards,
Andrei
Average Rating:



1 rating
|
Sign in to rate this
Hi Andrei,
What communication method do you have set for supplier site? Email
Please also check profiles mentioned on Purchase Order Communication: How to To Enable/Disable Purchase Order Communication With The Supplier And/Or Override The Default Supplier E-mail? (Doc ID 2237654.1)
PO_CONTROL_SUPPLIER_COMMUNICATION is enabled but end dated and when I try to remove it. The save butting was greyed out and note displaying as This data is protected against edits. All changes will be lost
how to edit the profile ?
Average Rating:



1 rating
|
Sign in to rate this
Thanks for sharing screenshot.
Please review: PRC:PO: Why Is The Profile Option - Control Supplier Communication End Dated (Doc ID 2186181.1)
So do disregard the end date.
You also did not reply to : -If you open the PO from UI and you try via: Actions - Communicate, is this sent?
Check setup again, and if you are unable to figure it out, document the setup and open an SR.
Cheers,
Andrei
Average Rating:



1 rating
|
Sign in to rate this
Thanks Andrei for your information, i checked that note it seems it required SR to disable to date
Reply to : -If you open the PO from UI and you try via: Actions - Communicate, is this sent?
attached screen shot
Average Rating:



1 rating
|
Sign in to rate this
Hi, Thanks for the picture but still not clear.
If you go from PO UI -> Actions - > communicate -> OK
Do you get the email? or not?
Average Rating:



1 rating
|
Sign in to rate this
No, I didn't get any email
is this because profile option PO_CONTROL_SUPPLIER_COMMUNICATION end dated ?
Average Rating:



1 rating
|
Sign in to rate this
Hey, I do not believe this is affected by the end date.In regards to your end date question, as I told you earlier please review:
PRC:PO: Why Is The Profile Option - Control Supplier Communication End Dated (Doc ID 2186181.1)
Also review Yeshika's update:
If you cannot figure it out, document the setup and open an SR.
Cheers,
Andrei
Average Rating:



1 rating
|
Sign in to rate this
attached picture
Average Rating:



1 rating
|
Sign in to rate this
Did you attach anything on this Piyush?
Average Rating:



1 rating
|
Sign in to rate this
Yeah attached the picture of profile option
Average Rating:



1 rating
|
Sign in to rate this
Average Rating:



1 rating
|
Sign in to rate this
Average Rating:



2 ratings
|
Sign in to rate this
Thanks Andrei and Yeshika for your input.
i have done the setup but still it is not working.
i had open Oracle SR and they are working on it.